Within what time frame must a black start unit be able to close onto a dead bus?

Prepare for the PJM Generation Dispatcher Exam with flashcards and multiple choice questions. Each question includes hints and explanations to maximize your study efficiency. Ensure you’re ready to pass your exam confidently!

A black start unit must be capable of closing onto a dead bus within a specific timeframe to play its critical role in restoring power after a blackout. The correct answer indicates that this timeframe is 3 hours.

The requirement for black start capabilities is essential to ensure that a unit can re-energize a grid section that lacks power. This involves the unit being able to operate independently of the larger electrical system until sufficient generation is restored to allow a seamless transition back to normal operations.

Meeting the 3-hour requirement ensures that the black start unit can respond effectively in the event of a system-wide failure, allowing for a timely and controlled restoration process. This timeframe balances the need for rapid response while providing adequate time to ensure that the unit is fully operational and ready to energize the dead bus safely.

Understanding this timeframe is crucial for operators to implement contingency plans effectively and ensure that the grid can return to operational status as quickly as possible following a major outage.