When should planned outages be submitted?

Prepare for the PJM Generation Dispatcher Exam with flashcards and multiple choice questions. Each question includes hints and explanations to maximize your study efficiency. Ensure you’re ready to pass your exam confidently!

The appropriate timeframe for submitting planned outages is no later than 30 days in advance. This requirement ensures that all members of the grid have adequate notice to adjust their operations and maintain system reliability while accommodating the necessary maintenance or upgrades to generation facilities. By adhering to this timeline, system operators can effectively manage the supply-demand balance and mitigate potential disruptions that can arise from unplanned generation deficiencies.

Submitting at least 30 days in advance provides sufficient time for coordination among various stakeholders, including other generation providers, transmission operators, and market participants, ensuring a seamless integration of planned maintenance into the overall operation of the grid.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy